Interstate 57/74 Interchange Reconstruction

Traffic Impacts

All ramp closures for the I-57/I-74 interchange project will have the following: 7 day notice using Changeable Message Boards on the interstate, a press release and a marked detour.

*Scheduled work dates subject to change.

Upcoming I-57/I-74 Ramp Closures:

  • I-57 SB to I-74 EB

Future closures to build piers for the new structures:

  • I-74 EB to I-57 NB: 2 week duration
  • I-74 WB to I-57 SB: 2 week duration
  • I-57 NB to I-74 WB: 6 week duration

I-57/74 Interchange Project Big Picture View

Click here to view

Setting the beams for the 2 flyover bridges, which is tentatively scheduled for the summer of 2023,  will result in full interstate and ramp closures at night only.  The interchange reconstruction project is progressing on schedule.

The I-74 bridges over Market Street and the Canadian National Railroad are progressing on schedule.  Traffic will be switched back to the normal configuration (crossover removed) within the next few weeks.  This year’s work will be completed by November 24th  weather permitting.

Work on University Avenue required to meet the completion date was completed by November 1st. Minor work including seeding, sodding and clean up will be completed by mid-November weather permitting.