SCAM ALERT: A current text message smishing scam claims recipients owe money associated with traffic tickets, tolls and other fines. These are not legitimate messages from the Illinois Department of Transportation. If you receive a message report it to the Federal Trade Commission and/or the FBI’s Internet Crime Complaint Center.

I-270 Designed Overlay and Structure Repairs

District 8

Delivery Method: Design-Build (DB)

Project Summary

The project scope includes the removal and replacement of the roadway surface, minor geometric improvements to the IL 157 and IL 159 interchanges, drainage improvements, shoulder improvements, safety upgrades, and structure repairs and rehabilitations along I-270 from IL 111 to east of I-55/70 in Glen Carbon, Madison County, Illinois. The scope of structure repairs includes one full bridge replacement, two deck replacements, and minor repairs to approximately 20 additional structures. The total project length is approximately 9 miles, and the construction cost is estimated to be $220,000,000.

Location – Glen Carbon, IL

Project Goals

  • Improve the pavement and bridge conditions by overlaying the highway and repairing existing structures to provide a long-lasting and durable corridor that minimizes future maintenance.
  • Provide construction staging and maintenance of traffic that balances impacts to the traveling public while minimizing the construction duration.
  • Upgrade corridor geometrics, traffic barriers and attenuation, and infrastructure to current standards.

Project Milestones

COMPLETE

Planning Phase:

Written Determination                     

October 21, 2025

Revised Written Determination

April 1, 2026

Pre-Procurement Phase:

Notice of Intent (NOI)                     

July 06, 2026

Industry Forum #1

January 21, 2026

Industry Forum #2

July 13, 2026

IN-PROGRESS

Procurement Phase:

Issue the Request for Qualifications (RFQ)    

July 29, 2026             

Statements of Qualifications (SOQ) Due

August 31, 2026

Notification of Shortlisted Proposers

October 01, 2026

Issue the Request for Proposals (RFP)

October 15, 2026

Proposals Due

Winter 2027

DB Selection

Spring 2027

ANTICIPATED

Implementation Phase:

Construction start                                   

Anticipated in 2027

Project Completion

TBD

Project Team

  • Design-Build Team: TBD

Project Documents

Why utilize Design-Build (DB) Delivery?

Project improvements are accelerated by combining design and construction under a single contract, fostering collaboration, allowing for innovative procedures, and improving cost and schedule certainty.