I-270 Designed Overlay and Structure Repairs
District 8
Delivery Method: Design-Build (DB)
Project Summary
The project scope includes the removal and replacement of the roadway surface, minor geometric improvements to the IL 157 and IL 159 interchanges, drainage improvements, shoulder improvements, safety upgrades, and structure repairs and rehabilitations along I-270 from IL 111 to east of I-55/70 in Glen Carbon, Madison County, Illinois. The scope of structure repairs includes one full bridge replacement, two deck replacements, and minor repairs to approximately 20 additional structures. The total project length is approximately 9 miles, and the construction cost is estimated to be $220,000,000.
Location – Glen Carbon, IL
Project Goals
- Improve the pavement and bridge conditions by overlaying the highway and repairing existing structures to provide a long-lasting and durable corridor that minimizes future maintenance.
- Provide construction staging and maintenance of traffic that balances impacts to the traveling public while minimizing the construction duration.
- Upgrade corridor geometrics, traffic barriers and attenuation, and infrastructure to current standards.
Project Milestones
Planning Phase:
|
Written Determination |
October 21, 2025 |
|
Revised Written Determination |
April 1, 2026 |
Pre-Procurement Phase:
|
Notice of Intent (NOI) |
July 06, 2026 |
|
Industry Forum #1 |
January 21, 2026 |
|
Industry Forum #2 |
July 13, 2026 |
Procurement Phase:
|
Issue the Request for Qualifications (RFQ) |
July 29, 2026 |
|
Statements of Qualifications (SOQ) Due |
August 31, 2026 |
|
Notification of Shortlisted Proposers |
October 01, 2026 |
|
Issue the Request for Proposals (RFP) |
October 15, 2026 |
|
Proposals Due |
Winter 2027 |
|
DB Selection |
Spring 2027 |
Implementation Phase:
|
Construction start |
Anticipated in 2027 |
|
Project Completion |
TBD |
Project Team
- Design-Build Team: TBD
Project Documents
Why utilize Design-Build (DB) Delivery?
Project improvements are accelerated by combining design and construction under a single contract, fostering collaboration, allowing for innovative procedures, and improving cost and schedule certainty.