I-39 Kishwaukee River Bridge Project
District 2
Delivery Method: Progressive Design-Build (PDB)
Project Summary
The Project will replace the existing dual bridges that carry Interstate 39 (I-39) over the Kishwaukee River south of Rockford in Winnebago County. The new bridges are expected to improve safety and mobility by adding one travel lane in each direction, providing three 12- foot lanes for northbound and southbound traffic. The existing bridges are notable structures: they were the first of their kind built in Illinois and the first in the United States constructed using a launching truss. The current estimated construction cost is $106,000,000.
Location – Winnebago County, IL
Project Goals
- Full replacement of the I-39 dual bridges over the Kishwaukee River.
- Minimize construction impacts to the motorized public, surrounding forest preserves, and adjacent communities.
- Construct final improvements within existing Right-of-Way (ROW).
- Maintain a minimum of 2 lanes southbound, 1 lane northbound on I-39 during construction.
- Utilize the Progressive Design-Build delivery method to accelerate the replacement of the structures.
Project Milestones
Planning Phase:
|
Written Determination |
August 06, 2025 |
Pre-Procurement Phase:
|
Notice of Intent (NOI) |
August 14, 2025 |
|
Industry Forum |
September 22, 2025 |
Procurement Phase:
|
Issue the Request for Qualifications (RFQ) |
October 24, 2025 |
|
RFQ Request for Clarification (RFC) Due |
November 5, 2025 |
|
Issue RFQ Addendum #1 |
November 13, 2025 |
|
Issue RFQ Addendum #2 |
November 18, 2025 |
|
Statements of Qualifications (SOQ) Due |
November 26, 2025 |
|
Notification of Shortlisted Proposers |
February 4, 2026 |
|
Issue the Request for Proposals (RFP) |
February 12, 2026 |
|
Issue RFP Addendum #1 |
March 10, 2026 |
|
RFP Request for Clarification (RFC) Due |
March 17, 2026 |
|
Issue RFP Addendum #2 |
March 18, 2026 |
|
Issue RFP Addendum #3 |
March 27, 2026 |
|
Proposals Due |
April 10, 2026 |
|
CMGC Selection |
May 11, 2026 |
Implementation Phase:
|
Pre-Construction Services Notice to Proceed (NTP1) |
August 24, 2026 |
|
Anticipated Construction Start |
March 2027 |
Project Team
- Progressive Design-Build Team: Kraemer North America and Burns & McDonnell
Project Documents
Why utilize Progressive Design-Build Delivery?
Progressive Design-Build brings the designer, contractor, and IDOT together early to identify challenges, manage costs, and plan construction activities more effectively. This helps reduce delays, limit surprises, and deliver improvements with fewer impacts to the public.