Project Summary
The Project includes the replacement of the bridge carrying IL 4/15 over the Kaskaskia River, as well as two adjacent overflow structures located east of the river near Fayetteville in St. Clair County, Illinois. This bridge provides one of the few links across the Kaskaskia River in the region, serving the trucking and agricultural industries, in addition to commuters of neighboring towns to their destinations. Without this vital link across the Kaskaskia River, the shortest alternative route would add approximately 30 miles to a trip. The construction cost is estimated at $87,500,000.
Location – Fayetteville, IL
Project Goals
- Reconstruct the truss bridge carrying IL 4/15 over the Kaskaskia River including approaches, overflow structures, and tie-ins to improve safety for bicycles and pedestrians, vehicular traffic, and farm traffic through the project area.
- Ensure that the existing bridge remains open to traffic or equivalent access is maintained during construction to minimize disruptions to local traffic, emergency services, and the farming community. Similarly, that the Kaskaskia River, a navigable waterway, remains open to recreational traffic during construction.
- Maintain a safe work zone and construction through effective risk identification and mitigation.
Project Milestones
Planning Phase:
|
Written Determination |
October 15, 2024 |
Pre-Procurement Phase:
|
Notice of Intent (NOI) |
December 31, 2025 |
|
Industry Forum |
January 20, 2026 |
Procurement Phase:
|
Issue the Request for Qualifications (RFQ) |
February 10, 2026 |
|
Issue RFQ Addendum #1 |
February 14, 2026 |
|
RFQ Request for Clarification (RFC) Due |
February 25, 2026 |
|
Statements of Qualifications (SOQ) Due |
March 05, 2026 |
|
Notification of Shortlisted Proposers |
March 26, 2026 |
|
Issue the Request for Proposals (RFP) |
April 06, 2026 |
|
Issue RFP Addendum #1 |
April 10, 2026 |
|
Issue RFP Addendum #2 |
April 29, 2026 |
|
RFP Request for Clarification (RFC) Due |
May 12, 2026 |
|
Issue RFP Addendum #3 |
May 14, 2026 |
|
Issue RFP Addendum #4 |
May 21, 2026 |
|
Issue RFP Addendum #5 |
May 27, 2026 |
|
Proposals Due |
June 4, 2026 |
|
Notice of Intent to Award / CMGC Selection |
July 27, 2026 |
Implementation Phase:
|
Pre-Construction Services Notice to Proceed (NTP1) |
September 11, 2026 |
|
Construction start |
Anticipated in 2027 |
|
Project Completion |
TBD |
Project Team
- CMGC - Ames Construction
- Engineer-of-Record - Horner & Shifrin, Inc.
Project Documents
Why utilize Construction Manager / General Contractor (CMGC) Delivery?
By engaging a Contractor early during design, IDOT can better manage risk, address complex construction challenges, and deliver the best value to the public.