Skip to main content

SCAM ALERT: A current text message smishing scam claims recipients owe money associated with traffic tickets, tolls and other fines. These are not legitimate messages from the Illinois Department of Transportation. If you receive a message report it to the Federal Trade Commission and/or the FBI’s Internet Crime Complaint Center.

IL 4/15 Kaskaskia River Bridge Project

District 8

Delivery Method: Construction Manager / General Contractor (CMGC)

Project Summary

The Project includes the replacement of the bridge carrying IL 4/15 over the Kaskaskia River, as well as two adjacent overflow structures located east of the river near Fayetteville in St. Clair County, Illinois. This bridge provides one of the few links across the Kaskaskia River in the region, serving the trucking and agricultural industries, in addition to commuters of neighboring towns to their destinations. Without this vital link across the Kaskaskia River, the shortest alternative route would add approximately 30 miles to a trip. The construction cost is estimated at $87,500,000.

Location – Fayetteville, IL

Project Goals

  • Reconstruct the truss bridge carrying IL 4/15 over the Kaskaskia River including approaches, overflow structures, and tie-ins to improve safety for bicycles and pedestrians, vehicular traffic, and farm traffic through the project area.
  • Ensure that the existing bridge remains open to traffic or equivalent access is maintained during construction to minimize disruptions to local traffic, emergency services, and the farming community. Similarly, that the Kaskaskia River, a navigable waterway, remains open to recreational traffic during construction.
  • Maintain a safe work zone and construction through effective risk identification and mitigation.

Project Milestones

COMPLETE

Planning Phase:

Written Determination                    

October 15, 2024

Pre-Procurement Phase:

Notice of Intent (NOI)                           

December 31, 2025

Industry Forum

January 20, 2026

Procurement Phase:

Issue the Request for Qualifications (RFQ)

February 10, 2026    

Issue RFQ Addendum #1

February 14, 2026

RFQ Request for Clarification (RFC) Due

February 25, 2026

Statements of Qualifications (SOQ) Due

March 05, 2026

Notification of Shortlisted Proposers

March 26, 2026

Issue the Request for Proposals (RFP)

April 06, 2026

Issue RFP Addendum #1

April 10, 2026

Issue RFP Addendum #2

April 29, 2026

RFP Request for Clarification (RFC) Due

May 12, 2026

Issue RFP Addendum #3

May 14, 2026

Issue RFP Addendum #4

May 21, 2026

Issue RFP Addendum #5

May 27, 2026

Proposals Due

June 4, 2026

Notice of Intent to Award / CMGC Selection

July 27, 2026

IN-PROGRESS

Implementation Phase:

Pre-Construction Services Notice to Proceed (NTP1)         

September 11, 2026   

Construction start

Anticipated in 2027

Project Completion

TBD

Project Team

  • CMGC - Ames Construction
  • Engineer-of-Record - Horner & Shifrin, Inc.

Project Documents

Why utilize Construction Manager / General Contractor (CMGC) Delivery?

By engaging a Contractor early during design, IDOT can better manage risk, address complex construction challenges, and deliver the best value to the public.