I-290 Drainage Improvement Project
District 1
Delivery Method: Construction Manager / General Contractor (CMGC)
Project Summary
Serving as the western gateway to the City of Chicago, I-290 is a major link in the transportation network serving northeast Illinois. The Project is one of several projects to be completed as part of the larger I-290 Corridor Project. The scope of the Project includes drainage improvements extending from the Des Plaines River to east of Austin Boulevard along the Eisenhower Expressway (I-290) to alleviate flooding experienced along the corridor. The improvements will supplement the existing storm sewer system, connecting to and conveying drainage to IDOT’s Pump Station No. 4. The new storm sewer system is expected to be an underground tunnel. The current construction cost is estimated at $400,000,000.
Location – Chicago, IL
Project Goals
- Improve stormwater drainage and alleviate flooding along the I-290 Corridor.
- Reduce construction impacts on the environment, nearby communities, utilities, the Des Plaines River, and the traveling public, including road, rail, and pedestrian traffic.
- Advance design and construction efficiently to minimize delays and support coordination with adjacent I-290 improvements and long-term maintenance.
- Maintain a safe work zone and tunnel construction program through effective risk identification and mitigation.
- Support inclusive participation and clear public communication with local jurisdictions, partners, and stakeholders.
Project Milestones
Planning Phase:
|
Written Determination |
March 12, 2024 |
Pre-Procurement Phase:
|
Notice of Intent (NOI) |
October 29, 2024 |
|
Request for Information (RFI) |
November 12, 2024 |
|
Industry Forum |
December 9, 2024 |
Procurement Phase:
|
Issue the Request for Qualifications (RFQ) |
January 31, 2025 |
|
RFQ Request for Clarification (RFC) Due |
February 24, 2025 |
|
Issue RFQ Addendum #1 |
February 28, 2025 |
|
Issue RFQ Addendum #2 |
March 14, 2025 |
|
Statements of Qualifications (SOQ) Due |
March 25, 2025 |
|
Notification of Shortlisted Proposers |
April 29, 2025 |
|
Issue the Request for Proposals (RFP) |
May 14, 2025 |
|
Issue RFP Addendum #1 |
May 29, 2025 |
|
RFP Request for Clarification (RFC) Due |
May 30, 2025 |
|
Issue RFP Addendum #2 |
June 13, 2025 |
|
Issue RFP Addendum #3 |
July 2, 2025 |
|
Issue RFP Addendum #4 |
July 22, 2025 |
|
Proposals Due |
July 25, 2025 |
|
CMGC Selection |
September 12, 2025 |
Implementation Phase:
|
Pre-Construction Services Notice to Proceed (NTP1) |
December 10, 2025 |
|
Anticipated Construction Start |
2027 |
|
Project Completion |
TBD |
Project Team
- Construction Manager / General Contractor: Granite Construction Company
- Engineer-of-Record: H.N.T.B. Corp.
Project Documents
Why utilize Construction Manager / General Contractor (CMGC) Delivery?
By engaging a Contractor early during design, IDOT can better manage risk, address complex construction challenges, and deliver the best value to the public.