The Illinois Department of Transportation (IDOT), along with financial support of the Iowa Department of Transportation, has awarded a contract to remove and replace the structure carrying US 52/IL 64 over the Mississippi River.  This project was let on September 19, 2015 and awarded to Kraemer North America for $80.6 million dollars.  Construction activities began in January 2016 and will conclude prior to May 31, 2018.

This site will be updated periodically as the project progresses. The Illinois Department of Transportation (IDOT) wishes to thank you for your support and patience.

Scope

Proposed Work

Contract 64G59 includes the removal and replacement of the existing structure and roadway improvements along the Iowa causeway and IL 84.  To following link will access the contract plans:

https://apps1.dot.illinois.gov/eplan/DESENV/091815/01X-64G59/

Details

Project Updates

Two cameras will be installed to record worksite activities and progress. The images from the video camera website will also be provided for viewing from this link with a minimum refresh rate of 15 seconds. 

Maintenance of Traffic

One lane of traffic will be maintained at all times with the use of flaggers and signals.

Schedule

11/7/17 – The proposed structure will be open to traffic mid-November 2017. The existing structure will be removed prior to April 1, 2018. All work shall be completed by May 2018.
The ribbon cutting event will take place on November 17, 2017 at 1 pm in Savanna on the new structure.

Maintenance of Traffic Schedule

Contact Us

As the U.S. 52/IL 64 Over the Mississippi River Study progresses, we will regularly update this website to ensure you are kept informed. The study team is interested in hearing your ideas and opinions! If you have questions or comments about the study, please fill out the Question/Comment Submittal Form, or write to us at:

Paul A. Loete, P.E.
Deputy Director of Highways
Region Two Engineer
Illinois Department of Transportation
819 Depot Avenue
Dixon, Illinois 61021-3500