Sugar Camp
Contracts and Plans
April 23, 2010 IDOT Letting
Item No. 271 Contract No. 98907
Wetland mitigation located along Sugar Camp Creek, 8 miles north of Benton; includes 405 shrubs; 156 units seedlings; 4,220 gals weed control; 13 cu yds concrete for drainage control structures; 33,755 cu yds earth excavation; 42.25 acres seeding; 80 acres mulch; 765 lbs reinforcement bars; 9,347 ft perimeter erosion barrier; mobilization. (Completion Date: June 30, 2011) (Job No. C-99-019-05) (9-00252-0200) (See Special Provisions for DBE %)
June 15, 2012 IDOT Letting
Item 164 - Contract No. 78278
This project consists of constructing 2 drainage control spillway structures and wetland plants and trees located along Sugar Camp Creek in Franklin County, approximately 8 miles northeast of Benton.