IDOT’S THREE-PHASE PROJECT DEVELOPMENT PROCESS

Proposed highway improvements are typically processed in three phases.  In Phase I (preliminary engineering phase), proposed geometry, environmental concerns, and right-of-way requirements are defined.  This phase generally takes an estimated 24 months to complete.  During Phase II, contract plans are prepared, and the necessary right-of-way is acquired.  This phase generally takes an estimated 12-24 months to complete.  Phase III represents the actual construction of the improvement.  This phase generally takes an estimated 18-24 months to complete. This project is currently in Phase II.