SCAM ALERT:  A current text message smishing scam claims recipients owe money associated with traffic tickets, tolls, and other fines.  These are not legitimate messages from the Illinois Department of Transportation.  If you receive a message report it to the Federal Trade Commission and/or the FBI’s Internet Crime Complaint Center.

Project Process

IDOT utilizes a three Phase process for advancing projects. Phase I Engineering identifies the Purpose and Need of the project, completes environmental reviews and conducts preliminary design for the project. Phase II is the Design phase which refines the design and develops Plans, Specifications and Estimates for construction. Should any land acquisition be needed for a project, this process takes place during Phase II. Phase III is the construction, and final phase of a project.