SCAM ALERT: A current text message smishing scam claims recipients owe money associated with traffic tickets, tolls and other fines. These are not legitimate messages from the Illinois Department of Transportation. If you receive a message report it to the Federal Trade Commission and/or the FBI’s Internet Crime Complaint Center.

Welcome to IDOT's new website design! The address for some web pages has changed, so be sure to update any saved favorites as needed.

Interstate 55 at Illinois 59 Access Project


The Illinois Department of Transportation (Department) in partnership with the City of Joliet has completed preliminary engineering and environmental studies (Phase I) for the I-55 at IL 59 Access Study in Will County.

The study limits are bounded by Interstate 80 (I-80) on the south, US 52 on the north, Houbolt Road on the east and River Road on the west. 

The study focused on the I-55 interchange access and included the supporting local roadway network within the entire study area.  The preferred alternative received concurrence from the Federal Highway Administration on September 13, 2018 and includes the following four independent improvements.  Click on each project to access a color depiction of the improvements for each:

Click the link to view the proposed improvements

US 52 from River Road to Houbolt Road

  • Improvements include the widening of US 52 from east of River Road to Houbolt Road to provide two travel lanes in each direction, a median and a shared use path throughout the corridor.  There are also additional turn lanes being proposed at intersections.
  • In 2025 the project began Phase II, Contract Plan Preparation and Land Acquisition.  Phase II is anticipated to require 3 years to complete.
  • Phase III, construction will only begin once Phase II is complete and is dependent on future funding.
  • The project is included in the Department’s multi-year transportation program.

I-55 from I-80 to US 52

  • Construction is complete for this project. It converted the existing partial access interchange at I-55 and IL 59 into a full access diverging diamond interchange and the addition of auxiliary lanes on I-55 between its interchanges with IL 59 and IL 52.

Olympic Boulevard from I-55 East Frontage Road to Houbolt Road

  • This project is under construction and is being led by the City of Joliet.
  • The project improvements include the extension of Olympic Boulevard to the East Frontage Road of I-55

Seil Road from Raven Road to IL 59

  • This project is under construction and is being led by the Village of Shorewood.
  • The project improvements include mini roundabouts at the Seil Road intersections with Raven Road and States Lane

US 52 from River Road to Houbolt Road

  • This project is being led by the Illinois Department of Transportation.
  • Contract plan preparation and the land acquisition process for the US 52 from River Road to Houbolt Road project are underway.
  • As information becomes available, it will be posted here.

I-55 from I-80 to US 52

Olympic Boulevard from I-55 East Frontage Road to Houbolt Road

  • This project is being led by the City of Joliet.  Please direct any inquiries to the City of Joliet Public Works Department publicworks@joliet.gov

Seil Road from Raven Road to IL 59

  • This project is being led by the Village of Shorewood.  Please direct any inquiries to the Village of Shorewood Public Works Director, Noriel Noriega nnoriega@shorewoodil.gov

US 52 from River Road to Houbolt Road

I-55 from I-80 to US 52

Olympic Boulevard from I-55 East Frontage Road to Houbolt Road

  • This project is being led by the City of Joliet.  Please direct any inquiries to the City of Joliet Public Works Department publicworks@joliet.gov

Seil Road from Raven Road to IL 59

  • This project is being led by the Village of Shorewood.  Please direct any inquiries to the Village of Shorewood Public Works Director,  Noriel Noriega nnoriega@shorewoodil.gov

Public Hearing Materials

A public hearing was held at Joliet Junior College on October 10, 2024 from 4:00 PM to 7:00 PM.  Following are materials presented at the meeting.

Presentation slides with script English

Presentation slides with script Spanish

Exhibits

Brochure English and Spanish

Traffic Noise Analysis

4(f) De Minimis Report

Newsletter

 

Public Meeting Materials

Public meetings were held on September 14, 2017, April 11, 2018 and August 4, 2020.  Materials from each of the meetings can be accessed below.

 

Public Meeting No. 1 September 14, 2017

Presentation

Exhibits

Brochure

 

Public Meeting No. 2 April 11, 2018

Presentation

Exhibits

Brochure

 

Public Meeting No. 3 August 4, 2020

Presentation

Exhibits

Brochure

US 52 from River Road to Houbolt Road

Or

 I-55 from I-80 to US 52

Please direct any inquiries to the following link.  https://apps1.dot.illinois.gov/WER/?from=1

Olympic Boulevard from I-55 East Frontage Road to Houbolt Road

  • This project is being led by the City of Joliet.  Please direct any inquiries to the City of Joliet Public Works Department publicworks@joliet.gov

Seil Road from Raven Road to IL 59

  • This project is being led by the Village of Shorewood.  Please direct any inquiries to the Village of Shorewood Public Works Director, Noriel Noriega nnoriega@shorewoodil.gov