State Highway Roadway Improvement Projects - Perry County
Illinois 152, U.S. 51, and Illinois 14
A public meeting will be held on Oct. 25. Please see flyer below to learn more and comment.
A public meeting was held on October 25, 2023. View the flyer below to learn more.
Note: IDOT projects typically have three distinct phases. Phase I (or the project Study) consists of developing the project scope, environmental studies and preliminary design of a project. Phase II (Design) consists of refining the design to develop contract plans and land acquisition. Phase III (Construction) consists of the actual construction of the project.
Illinois 152 |
U.S. 51 |
Illinois 14 |
Overview Aerial Photography with Proposed Improvements Illinois 127 to Shady Oak Road Shady Oak Road to Beaucoup Creek Beaucoup Creek to Cudgetown Road Cudgetown Road to 0.5 miles east 0.5 miles west to Landfield Road Sourgum Road to 0.5 miles east 0.5 miles west to Sacred Heart Road Sacred Heart Road to Butternut Road Butternut Road West to Butternut Road East Butternut Road East to Little Woods Lane Little Woods Lane to West Street Typical Sections |
Overview Aerial Photography with Proposed Improvements Typical Sections |
Overview Aerial Photography with Proposed Improvements Typical Sections |
Updates
- Illinois 152 from U.S. 51 to Illinois 127 west of Du Quoin: Currently in the design phase (Phase II) and tentatively scheduled for construction in late 2026.
- U.S. 51 from Park Street to Stacy Street in Du Quoin: Construction is complete except for some minor items. The road is fully open.
- Illinois 14 from U.S. 51 to Old Illinois 14 south of Du Quoin: Tree removal and utility relocations are currently underway. Road work is expected to begin in Spring 2026.